Experiences of the PPP solution for the Arlanda rail link (RiR 2016:3)
The public-private partnership model, PPP, for the Arlanda rail link has essentially worked well. The audit conducted by the Swedish NAO shows that there are lessons to be learned if PPP is to be used for future infrastructure projects
Share in social media and by e-mail
Contact form
Send your questions or comments via the form below and we will make sure that they reach the right member of staff. Please state if your question concerns the information on this particular page.